Update 7-11 OBP is back in the news. On July 13th a judge ruled that the City illegally granted waviers to the developer in violation of a statute that was voted on in an election in 2005. The judge decreed there should be another election if the terms were to be changed. The City is deciding whether to appeal. OC Register Story. That 2005 election was very costly for the developer. Update 3-11 Nothing much visable is happening. The site has been graded but no tenants/no construction. The rumor mill says construction will begin in the Summer of 2011. The OBP website is dead. Update 4-07 Santa Ana Planning Department at WSNA neighborhood meeting: site clearing and preliminary work has begun. Harrah does not have the required percentage of committed tenants yet. Because the project was approved by a vote of the people, it make take another vote to change the terms to allow construction without the required tenants. Update 11-06 From Jeff Dickman, French Park (against the project) Subject: OBP Update Good morning all. Yesterday afternoon Joann Rameriz, Thomas Gordon and I met with Vince Fregoso from the City's Planning Department, to discuss Harrah's progress in meeting his list of requirements to proceed with construction of OBP. As most of you are aware, Harrah has received approval for: * Exterior design of the lower portion of OBP * Its Plaza design, and * Parking structure design Regarding the physical site of OBP, Harrah has: * Demolished the Yale Apartments * Demolished the 1960's era building at the corner of Broadway and Tenth * Scarified the top 1 foot of soil of the site, and * Is in process to move the Twist-Basler House Harrah has hired a company to move the house.Analysis continues to focus on the connection of the original house and the later additions. Both the house and its additions are to be relocated to the Tennis Club site per city conditions of approval. That said, Harrah has not accomplished the following required tasks: * Must still acquire the property at Main and 17th, and Broadway and 17th. (because of Harrah's delay the Gas Station project at Broadway and 17th is proceeding to construction - this means it will cost Harrah more to acquire the site). * Harrah must also acquire the four corners of land at Tenth and Sycamore. (One of the landowners there is the State of California) * Has not placed funds in a trust for other off-site road improvements. (Harrah has until December 1, 2006 to do this. The City likely extend the deadline. If Harrah fails to act by the end of 2007, the City may need to undertake the acquisitions. * Harrah has not proved he has 50% tenancy (Vince says he has not met with Harrah for 4 months - no reason). * Harrah has not submitted site plan (This will require up to 6 months to review - this may push him beyond his summer window for pile-driving to avoid the school year.)
|
||||
News and Activity Information |
||||
|
||||